Building Information Modeling:
A Holistic Approach to Facility Design and Planning
What is Involved?
Industry practice has been for architects and engineers to use
Computer Aided Design (CAD) software for planning and designing a
new facility or retrofit project. Sets of two-dimensional drawings
are produced and used to construct the building. From these sheets,
Scopes of Work are developed to be bid and completed by various
trades, changes to the design are tracked on site, and a post
construction "As-built" revision of the original design is recorded
and left with the building Owner for their records. Due to the
static nature and hierarchy of this process, there is increased
risk for common coordination issues to arise, and for information
to be missed, resulting in schedule delays while RFI's are
answered.
Figure 1: Using a 3D modeling program to
design all systems within the building, design disciplines can work
together to more effectively coordinate space requirements,
designing a leaner, more efficient building.

click to enlarge
Clash detection can occur during design, reducing RFI's once the
project gets to the construction phase. For example if a light
fixture is placed in the path of a supply duct, this could be a
problem during construction, wasting time and money, and could
result in the electrician having to return to the site to move the
light fixture, or an RFI to the design team to redesign the duct
work. A project using BIM can identify the conflict during design,
saving the owner time and money before those issues arise during
construction.
Photo courtesy of RLF
With advances in computer technology, there is a change moving
through the building design and construction industry. The
Architectural and Engineering (A/E) community, as well as many
general contractors, is increasingly implementing Building
Information Modeling (BIM). BIM is the process of building a 3D
data rich model of all architectural, structural, mechanical and
electrical systems in the building. The model is not only used to
design the building and document it for construction, it's also
used as the primary tool to create and coordinate design solutions.
"It really is a game changer," says Keith Holloway, a Project
Manager with RLF. "A lot of companies are trying to treat it like a
traditional drafting tool, but doing it that way just adds extra
steps that aren't necessary and are counter productive to the end
deliverable."
When using BIM on a project, early involvement of all parties
responsible for final completion of the facility is recommended.
Everyone including the owner, architect, design engineers, general
contractor, and associated trades have input in the process from
the beginning. This early input means combining field experience
with vision and the BIM model helps merge real-world with
design-world. Much of the reason that there is a need to create
as-built documentation following construction is the fact that
adjustments are made in the field, whether it be for
constructability, cost savings, etc. It is often the case that
'rules of thumb' may be applied during the early stages of design
and will remain unless and until they are vetted out by the design
team and owner. On large projects it is possible that these items,
especially if small by relative significance, go unnoticed until
the tradesman is trying to route equipment or apply a finish that
can't be done to specification.
In addition to creating and detailing design solutions, BIM
increases coordination among the many disciplines involved in the
building delivery process. As mentioned before, the more typical
practice is for A/E firms to produce electronic drawings for a
project that include two dimensional 'floorplan' layouts on a
by-floor or by-section basis. The architectural views within this
electronic CAD file act as the background and layout for spacial
reference of the engineering systems and other infrastructure.
Layers are then placed over top of this reference to view
mechanical, electrical, structural, plumbing, fire protection, and
any assortment of other specialty systems or details that need be
applied. Working in 2D means that many calculations and
measurements are done outside the CAD model, to ensure everything
will fit above the specified ceiling height, or to do area take
offs for cost estimating. This process leaves a lot of room for
error, as the structural engineer who is planning beam depths is
simultaneously doing their calculations with the mechanical
engineer who is sizing ductwork.
Verticality is Key
Applying a third dimension to the drawing set is not a new idea,
but allows for greater detail and understanding of the building.
Architects have applied three dimensions to their projects
throughout history to allow greater representation of the intended
finished product to the client. Models began as cutouts and
handmade structures to demonstrate orientation within surroundings
or proximity to other buildings within a campus. Naturally these
have progressed to simulated BIM renderings through programs like
Revit or Navisworks to review external finish work and perspectives
of the intended facility. What this provides is a greater depth of
understanding and analysis to members of the design team and
support staff. Being able to 'walk' through a hallway virtually,
see how daylighting plays across the room, what fixtures hang from
the ceiling above, to the detail of how ductwork will run from the
air handler to interior offices. This model is about reviewing and
ensuring that the owner's criteria and basis of design are met
efficiently while providing a look at the final result. The author
of 'Engineering-centric BIM' states that "Creating a
multidisciplinary 3D integrated model of a building is a valuable
tool…but if it does not enable interoperability, then it is not
truly BIM."
Advantageous to the Owner
However, increased coordination and better modeling are not the
only advantage of using BIM tools on a project. The following
benefits can also result from creating a 3D model before
construction begins:
- Promotes sustainable design through less material use and
integrated tools for energy and daylight simulation.
- Provides better information for cost estimating purposes. This
is very important when it comes to access issues and timing for
installation of critical, large, or specialty components.
- Promotes efficient scheduling; reducing costs associated with
rework in the field.
- Reduces materials being stored on site; creating a safer site
and less chance for items to be damaged prior to install.
- Allows analysis of alternative design options to resolve
conflicts early in the process and increase value.
BIM Still Improving: ASHRAE Headquarters
Remodel
Ultimately the goal of the BIM method is to create a single
packet of data referring to the building. This should include
energy modeling and performance analysis, even at the basic level,
to provide the owner with operational cost projections and
trade-offs from design decisions. The challenge lies in formatting
the data set to be compatible with the most appropriate energy/
daylight modeling software for the building type and proposed
systems. During a recent test of the BIM method by the American
Society of Heating Refrigeration and Air-conditioning Engineers
(ASHRAE), researchers conducted a trial using imported information
from a BIM model for their headquarters renovation and found that
the "models produce impressive graphics" but "BIM has been
overhyped" when it comes to the transition between different
programs to perform the needed tasks. Instead of being able to
directly transition the design data from the BIM program to the
energy analysis software, it became apparent that it would take
less time (and thus be less costly) to re-build the geometry and
systems in the energy model from scratch. These results were
reported in an article 'BIM Test at ASHRAE HQ'.
Despite its noteworthy advantages, BIM software has been widely
available for many years, without significant market adoption. Only
50% of the industry is using BIM, though it has been gaining
momentum since 2007. Whether it's because of software issues like
the one described above, firms can't afford the training or
expertise needed, or project budgets aren't structured to
accommodate the early effort, BIM seems to still be up and coming.
But for the design and construction firms that have embraced BIM,
the benefits far outweigh the costs. Seventy percent of BIM users
who measure ROI see positive returns.
Case Study: Veterans Affairs Medical Center,
Orlando Florida
The reason BIM users are such proponents is because BIM has
advantages for every member of the design, construction and
operations teams. Figure 1 below shows how each member of the
Veterans Affairs Medical Center Team has a stake in the planning
process and is able to retrieve the specific data they require from
a central repository.
click to enlarge
Figure 2: Process and data flows in a project utilizing the BIM
approach.
Figure courtesy of RLF
Using BIM on a large and complicated project such as a medical
campus provided the team with the data necessary to conduct
analysis in other useful software packages, and in some cases,
export data back into the BIM model. This "streaming data concept"
allowed for increased coordination, and for each team member to
have the final information needed to complete their project
responsibilities. In addition, from the project initiation phase,
the BIM model was intended to be used by the contractor and
eventually the owner for facility management purposes.
Not only did the software provide a 3D model of the building for
design coordination purposes, but data was also extracted to manage
program, equipment counts and other information important to
project stakeholders. For example, Figure 2 below shows a data
table generated by the BIM program that compares client programming
requirements to those achieved by the final design solution. This
information was used to illustrate accomplishment of project goals
to the client, and it was used by medical planners during design to
develop an optimal solution.
The following benefits that were attributed to the use of BIM
were identified for the VA Medical Center project:
- Ability to manage costs and budgets
- Streamline the workflow
- Improve team communication
- Resolve conflicts
- Analyze design options
- Calculate lifecycle usage
These benefits were recognized by some of the key players in the
project, represented by these statements:
Architect:
"Due to the enormous scale of the project,...the use of BIM and
associated technologies has been key to providing an integrated
medical campus…"
Owner:
"The use of BIM has assisted the owner in numerous ways
including showing a three -dimensional fly-over… and developing
lists of equipment items. Information directly from BIM is used
as…procurement planning and preliminary equipment budgets"
Contractor:
"As construction began…it was extremely evident that the use of
BIM enabled the entire project team to identify and resolve
potential issues that may have had a substantial impact to the
future phases of the project."
In the Industry
As it stands currently, there is no formal oversight committee
or group that defines and manages what BIM entails and the extent
of its use. However, there are groups such as GSA, DOD and the VA
who are currently working to establish standards for BIM
solicitation and contract language, constructing BIM toolkits and
publishing BIM Guides. In addition, the buildingSMART Alliance,
part of the National Institute for Building Sciences (NIBS) is
developing a standard, dubbed NBIMS-US that is scheduled for
release in December 2011. There are many options for BIM software
available and appropriate software must be chosen carefully to
ensure accurate data sharing between software packages when
necessary. For example, AutoCAD, Revit or Navisworks, Radiance or
AGI32 (for lighting), and Design Builder or eQUEST (for energy
analysis) may be used on a single project. The selection of
software will also determine up front licensing costs and training
needs for the individuals utilizing the software.
Figure 3: Example Data Table Generated by BIM
|

click to enlarge |
For references and resources there are many networking and
professional groups that can provide lessons-learned about the BIM
process. Trade groups like the American Institute of Architects
(AIA) post articles and resources for designers. Multiple
user-groups have formed on sites like LinkedIn to network design
and construction individuals.
The exciting truth of BIM is that the concepts are not
necessarily new in and of themselves. Where the innovation comes is
the application of those same tools that we rely on for proper
design and construction to new points in the process and including
additional trained personnel to ensure quality design and delivery
becomes a reality. We design all manner of retail products in this
virtual environment to be reviewed and approved before the first
generation is off the line. Many of the same concepts apply to the
buildings we construct today. The result is one chance to build it
right and the effects of mistakes early on only compound time,
cost, and stress in team relationships. With the increasing use of
the BIM approach to facility design and planning, additional
advances will be made in modeling software integration and
centralization of project data. Trained professionals can also
begin to establish best-practices for use in the years to come.
| Training Highlights |
|
California utilities offer outstanding educational opportunities
that focus on the design, construction and operation of
energy-efficient buildings. Listed here are a few of the many
upcoming classes and events; for complete schedules, visit each
utility's website.
Financial Analysis of Energy-Efficiency Projects
This workshop will expand the definition of "owner-occupied",
overcoming myths and organizational inertia, find opportunities for
energy-efficiency improvement, and quantifying the benefits of
contemplated upgrades.
Friday February 10,
8:30 am to 4:30 pm
San Francisco - PEC
register
> |
EnergyPro Software for Beginners
EnergyPro computer training is designed for architects and others
involved in documenting Title 24 compliance. This class introduces
the basic input and modeling requirements used to document
commercial building envelope, lighting, and mechanical systems with
Title 24 Standards.
Thursday February 6,
8:30 am to 4:30 pm
Irwindale - Energy Education Center
register
>
|
Don't miss future issues - to sign up for a free email subscription, please visit our
newsletter subscription page. Send letters to the editor, suggestions on topics for future
issues, or other comments to the e-News editor via our
Comments & Feedback form.
e-News is published by Energy Design
Resources (www.energydesignresources.com),
an online resource center for information on energy efficiency design practices in
California.
Savings By Design (www.savingsbydesign.com)
offers design assistance and incentives to design teams and building owners in California
to encourage high-performance nonresidential building design and construction.
Energy Design Resources and Savings By Design are funded by California utility customers
and administered by Pacific Gas and Electric Company, Sacramento Municipal Utility
District, San Diego Gas and Electric, Southern California Edison and Southern California
Gas Company, under the auspices of the California Public Utilities Commission.